Flanking sound (or flanking noise) is sound that transmits between spaces indirectly, going over or around, rather than directly through the main separating element. This can allow sound to transmit between spaces even though the main separating element itself provides good acoustic insulation.
Approved document E: Resistance to the passage of sound, defines ‘flanking transmission’ as, ‘Sound transmitted between rooms via flanking elements instead of directly through separating elements or along any path other than the direct path’. It defines a ‘flanking element’ as, ‘Any building element that contributes to sound transmission between rooms in a building that is not a separating floor or separating wall’.
A common example of flanking is sound transmitted between two spaces through a floor void (or even a floating screed) that runs under the separating partition, even though the partition provides good acoustic insulation preventing the direct transmission of sound.
Flanking can result from both impact sounds and airborne sounds.
Any building element that penetrates or circumnavigates a separating element can result in flanking. This might include:
- Windows and doors.
- Flanking ceilings, floors and walls which continue past the separating element into the adjoining space.
- Voids such as wall cavities, suspended ceilings and raised floors.
- Penetrating joists.
- Corridors and other circulation spaces.
- Ductwork and pipework.
- Sockets.
- Poor workmanship.
Flanking should be considered early in the design stage of new developments and detailing should eliminate or minimise the inadvertent downgrading of sound insulation. Junctions between elements in particular can offer a potential flanking route if they are not carefully detailed and constructed. Good briefing, supervision and inspection on site can help to ensure that the quality of workmanship remains high so that details are constructed as designed.
Flanking can be a particular issue where adjoining spaces have different uses, such as; a lecture theatre next to an office, a private room adjacent to a circulation space, or between neighbouring houses with different patterns of occupancy and behaviour.
Flanking can be difficult to treat in older buildings, where the addition of sound insulation to one element simply reveals a flanking path through another.
Approved document E of the building regulations: Resistance to the passage of sound, sets out requirements for sound insulation between spaces and provides guidance on how to detail separating elements to avoid flanking.
BS EN ISO 10848-4:2010 provides a standard for the laboratory measurement of the flanking transmission of airborne and impact sound between adjoining rooms.
[edit] Find out more
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Twas the site before Christmas...
A rhyme for the industry and a thankyou to our supporters.
Plumbing and heating systems in schools
New apprentice pay rates coming into effect in the new year
Addressing the impact of recent national minimum wage changes.
EBSSA support for the new industry competence structure
The Engineering and Building Services Skills Authority, in working group 2.
Notes from BSRIA Sustainable Futures briefing
From carbon down to the all important customer: Redefining Retrofit for Net Zero Living.
Principal Designer: A New Opportunity for Architects
ACA launches a Principal Designer Register for architects.
A new government plan for housing and nature recovery
Exploring a new housing and infrastructure nature recovery framework.
Leveraging technology to enhance prospects for students
A case study on the significance of the Autodesk Revit certification.
Fundamental Review of Building Regulations Guidance
Announced during commons debate on the Grenfell Inquiry Phase 2 report.
CIAT responds to the updated National Planning Policy Framework
With key changes in the revised NPPF outlined.
Councils and communities highlighted for delivery of common-sense housing in planning overhaul
As government follows up with mandatory housing targets.
CIOB photographic competition final images revealed
Art of Building produces stunning images for another year.
HSE prosecutes company for putting workers at risk
Roofing company fined and its director sentenced.
Strategic restructure to transform industry competence
EBSSA becomes part of a new industry competence structure.
Major overhaul of planning committees proposed by government
Planning decisions set to be fast-tracked to tackle the housing crisis.
Industry Competence Steering Group restructure
ICSG transitions to the Industry Competence Committee (ICC) under the Building Safety Regulator (BSR).
Principal Contractor Competency Certification Scheme
CIOB PCCCS competence framework for Principal Contractors.
The CIAT Principal Designer register
Issues explained via a series of FAQs.